One of our report needs the calculation of ETC(Cost) at task level. While checking I get the general formula:

ETC (Cost): Cost of Estimate to Complete
ETC (Cost) = remaining labor cost (ETC * billing rate) + remaining non-labor cost

But I am not able find any matched database columns (it is a virtual attribute in Clarity). Expecting the table details where I can query the field.

4

1 回答 1

1

“Clarity/CA PPM”中的虚拟属性是“实时”计算的,因此您不会在任务表的字段中找到数据。

但是,有一个数据库视图,您可以在其中找到使用的 SQL 公式甚至结果(请注意,使用视图中的数据不是最佳做法)

检查视图:ODF_TASK_V 和 ODF_TASK_V2