我的项目时间表如下。我需要从启动会议的第 1 号开始 wbs。直到 Kick-off,我使用自定义的 wbs 代码,即 M1,M2,M3,M4。这是工作。从病房的启动会议开始,我需要开始 1 1.1 1.2、2、2.1、2.2 等

现有时间表

WBS  Task name
1 M1: Milestone1
2 M2: Milestone2
3 M3: Milestone3
4 M4: Milestone4
5 Kick-off meeting
6 Requirement
   6.1. Requirement collection
   6.2. Requirement priority
   6.3. Finalise requirements
7 Design
   7.1 High level design
   7.2 Low level design
8 Implementation
   8.1 coding
   8.2 code review
9 Testing
   9.1 Test plan
   9.2 Test case preparation
   9.3 Start Testing
10 Delivery
   10.1 Deliver to customer
   10.2 Release resource

我需要使用 wbs 代码在 WBS 上方进行更改,如下所示。

预计时间表

WBS  Task name
M1: Milestone1
M2: Milestone2
M3: Milestone3
M4: Milestone4
1 Kick-off meeting
2 Requirement
   2.1. Requirement collection
   2.2. Requirement priority
   2.3. Finalise requirements
3 Design
   3.1 High level design
   3.2 Low level design
4 Implementation
   4.1 coding
   4.2 code review
5 Testing
   5.1 Test plan
   5.2 Test case preparation
   5.3 Start Testing
6 Delivery
   6.1 Deliver to customer
   6.2 Release resource

我尝试使用 Project --> wbS -> Define code 和 Renumber,但两者都不起作用。

4

1 回答 1

1

使用自定义大纲代码,而不是内置 WBS 字段。然后,您可以按照自己的方式进行操作。将自定义代码命名为 CWBS 或 PWBS 或类似名称,以便区分它们。