我的项目时间表如下。我需要从启动会议的第 1 号开始 wbs。直到 Kick-off,我使用自定义的 wbs 代码,即 M1,M2,M3,M4。这是工作。从病房的启动会议开始,我需要开始 1 1.1 1.2、2、2.1、2.2 等
现有时间表
WBS Task name
1 M1: Milestone1
2 M2: Milestone2
3 M3: Milestone3
4 M4: Milestone4
5 Kick-off meeting
6 Requirement
6.1. Requirement collection
6.2. Requirement priority
6.3. Finalise requirements
7 Design
7.1 High level design
7.2 Low level design
8 Implementation
8.1 coding
8.2 code review
9 Testing
9.1 Test plan
9.2 Test case preparation
9.3 Start Testing
10 Delivery
10.1 Deliver to customer
10.2 Release resource
我需要使用 wbs 代码在 WBS 上方进行更改,如下所示。
预计时间表
WBS Task name
M1: Milestone1
M2: Milestone2
M3: Milestone3
M4: Milestone4
1 Kick-off meeting
2 Requirement
2.1. Requirement collection
2.2. Requirement priority
2.3. Finalise requirements
3 Design
3.1 High level design
3.2 Low level design
4 Implementation
4.1 coding
4.2 code review
5 Testing
5.1 Test plan
5.2 Test case preparation
5.3 Start Testing
6 Delivery
6.1 Deliver to customer
6.2 Release resource
我尝试使用 Project --> wbS -> Define code 和 Renumber,但两者都不起作用。