作为日历维度的一部分,我需要填充 iso_week_start_date、iso_week_end_date 和 iso_week_number。除了这些字段,我已经能够构建日历维度。谢谢。

4

1 回答 1

1

雪花优惠DATE_TRUNC(WEEK, ..)可让您获得 ISO 周的第一天。然后加上 6 天给你最后一天。还有DATE_EXTRACT(WEEK, ..)(或简单地说WEEK(..)

例如:

select extract(week, '2017-10-10'::date), date_trunc(week, '2017-10-10'::date), dateadd(day, 6, date_trunc(week, '2017-10-10'::date));
-----------------------------------+--------------------------------------+-------------------------------------------------------+
 EXTRACT(WEEK, '2017-10-10'::DATE) | DATE_TRUNC(WEEK, '2017-10-10'::DATE) | DATEADD(DAY, 6, DATE_TRUNC(WEEK, '2017-10-10'::DATE)) |
-----------------------------------+--------------------------------------+-------------------------------------------------------+
 41                                | 2017-10-09                           | 2017-10-15                                            |
-----------------------------------+--------------------------------------+-------------------------------------------------------+

请记住,ISO 周有一些奇怪的语义,请参阅文档了解更多详细信息。

于 2017-10-11T01:41:42.687 回答