我正在通过 MPXJ 库在 MS Project 中导出项目,我有一个问题:
如何将特定日期周六(或周日)设置为工作日而不是周末?(在 ProjectCalendar 或其他地方)
例如 2014 年 10 月 18 日(星期六)设置为工作日,但另一个星期六需要是周末。

public ProjectCalendar initCalendar(ProjectFile projectfile, int calendarId, Date startDate, Date endDate) { 
        ProjectCalendar defaultCalendar = projectfile.addDefaultBaseCalendar();

        /*Setup standart working week*/
        defaultCalendar.setName("Standart");
        defaultCalendar.setWorkingDay(Day.MONDAY, DayType.WORKING);
        defaultCalendar.setWorkingDay(Day.THURSDAY, DayType.WORKING);
        defaultCalendar.setWorkingDay(Day.WEDNESDAY, DayType.WORKING);
        defaultCalendar.setWorkingDay(Day.TUESDAY, DayType.WORKING);
        defaultCalendar.setWorkingDay(Day.FRIDAY, DayType.WORKING); 
        defaultCalendar.setWorkingDay(Day.SATURDAY, DayType.NON_WORKING);
        defaultCalendar.setWorkingDay(Day.SUNDAY, DayType.NON_WORKING);


        ProjectCalendarHours pch;
        pch = defaultCalendar.addCalendarHours(Day.MONDAY);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);

        pch = defaultCalendar.addCalendarHours(Day.THURSDAY);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);

        pch = defaultCalendar.addCalendarHours(Day.WEDNESDAY);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);

        pch = defaultCalendar.addCalendarHours(Day.TUESDAY);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);

        pch = defaultCalendar.addCalendarHours(Day.FRIDAY);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);


        /* setup holydays*/
        List<Date> workingHollidays = DBHelper.getWorkingHolidays(ppmCalendarId, startDate, endDate);
        for (Date work : workingHollidays) {
            ProjectCalendarException ex = defaultCalendar.addCalendarException(work, work);
        }

        /*There is  I need change stendart week and setup 6-days working week (Saturday is work day) */
        /*something like that*/
        Date workindDay = new SimpleDateFormat("dd.MM.yyyy").parse("18.10.2014");
        defaultCalendar.setWorkingDay(workindDay, DayType.NON_WORKING); // This code not work
        pch = defaultCalendar.addCalendarHours(workindDay); // This code not work
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);
    }

并且在输出中 Microsoft Project xml 将是这样的标记:

<Calendar>
    ...
    <WeekDay>
        <DayType>
            0
        </DayType>
        <DayWorking>
            1
        </DayWorking>
        <TimePeriod>
            <FromDate>2014-10-18T00:00:00</FromDate>
            <ToDate>2014-10-18T23:59:00</ToDate>
        </TimePeriod>
        <WorkingTimes>
            <WorkingTime>
                <FromTime>09:00:00</FromTime> 
                <ToTime>13:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
                <FromTime>14:00:00</FromTime> 
                <ToTime>18:00:00</ToTime>
            </WorkingTime>
        </WorkingTimes>
    </WeekDay>
    ...
</Calendar>

谢谢。

4

1 回答 1

1

我找到了答案。
有将自定义日期设为工作日期的代码:

Date workindDay = new SimpleDateFormat("dd.MM.yyyy").parse("18.10.2014"); 
ProjectCalendarException ex = defaultCalendar.addCalendarException(workindDay, workindDay);
ex.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
ex.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);

范围的顺序很重要。

于 2014-10-27T14:58:37.613 回答