0

我们最近开始将 TFS 2012 用于 SCRUM 方法,以下是我们当前的结构。我们在 Product Backlog 页面中显示 sprint 周期时遇到问题:

>     Team Project 1
>       |_Iteration 1
>          |_   Sprint 1 of Iteration 1 (Start Date: 04/7/2014 End Date: 04/25/2014) 
>       |_Iteration 2
>          |_   Sprint 1 of Iteration 2 (Start Date: 04/7/2014 End Date: 04/11/2014) 
>          |_   Sprint 2 of Iteration 2 (Start Date: 04/14/2014 End Date: 04/18/2014) 
>          |_   Sprint 3 of Iteration 2 (Start Date: 04/21/2014 End Date: 04/25/2014) 
>          |_   Sprint 4 of Iteration 2 (Start Date: 04/28/2014 End Date: 05/2/2014) 
>           
>           
>     When I look at the Product Backlog Page, this is what I see:
>     Current
>       |_  Sprint 1 of Iteration 1 (Start Date: 04/7/2014 End Date: 04/25/2014)    
>     Future
>       |_  Sprint 1 of Iteration 2 (Start Date: 04/7/2014 End Date: 04/11/2014) 
>       |_  Sprint 2 of Iteration 2 (Start Date: 04/14/2014 End Date: 04/18/2014) 
>       |_  Sprint 3 of Iteration 2 (Start Date: 04/21/2014 End Date: 04/25/2014) 
>       |_  Sprint 4 of Iteration 2 (Start Date: 04/28/2014 End Date: 05/2/2014)

backlog 页面显示的配置不正确,因为“迭代 2 的 Sprint 1”是过去完成的 sprint,正在显示未来,而“迭代 2 的 Sprint 2”是当前正在显示的 sprint。是否需要在 TFS 2012 中进行任何配置更改?

4

1 回答 1

0

您的迭代日期有问题。迭代不是并行处理的时间盒。您应该将它们视为上冲刺。

因此,在您的示例中,迭代 1 和 2 的 sprint 1 似乎是在同一日期开始的,而这样的事情不可能发生。在完成迭代 1 之前,您不能跳到迭代 2。我认为您将迭代用作项目分支,对吗?

于 2014-04-18T14:41:24.043 回答