the roll-up of tasks does not sum up the remaining amount of work for the userstory. If you go to a specific story and look at the lower level tasks under links they are not in sync with the userstory. we are using visual studio, scrum v2 on tfs 2010.

for ex: if there are 5 task in a user story, out which 1 task hour=8, rest zero. the total task hour sum up (i.e remaining hour) as 144 in user story.

Need help/suggestion/advice

4

1 回答 1

0

使用名为TFS Aggregator的第 3 方工具

此 TFS 2010 服务器端插件支持动态计算 TFS 中的字段值。(例如:开发工作 + 测试工作 = 总工作)。它支持相同的工作项和父子链接。它还支持聚合字符串值(即,子项已完成,因此父项已完成)。

于 2012-10-12T02:01:37.967 回答