In Microsoft Project (MSP), is it possible to have two parallel/concurrent activities with the same resource assigned to both? For example:

parallel tasks example

The worker resource "matt" is assigned to both activities, hence the overallocation error showing in the info column (red human icon).

Why do I require such a structure you may ask? In reality, one task would continually be temporarily interrupted to do the other one, and vice versa. But in MSP, it would be counter-productive to do so. Hence, my simplified approach - parallel activities.

So how should I fix this issue?

  • Ignore it?
  • Allocate 50% of the resource to each (and fix up finish dates which are automatically extended by MSP?)
  • Or is there a better solution?
4

2 回答 2

3

如果它们确实重叠,那么将其放入您的项目中的最佳方法是为每个任务分配 50%。但是为什么要修复完成日期,程序会根据新工作重新计算任务的新工期,而分配降低到 50% 那么工期应该加倍......或者你可以将任务声明为工期驱动,如果那样的话是这种情况,尽管分配发生了变化,但对于此类任务,持续时间将保持不变

于 2012-11-13T23:28:07.660 回答
1

I do not think there is a better solution. So solution number 2 that is adjusting assignment units is the best in your case.