In Microsoft Project (MSP), is it possible to have two parallel/concurrent activities with the same resource assigned to both? For example:
The worker resource "matt" is assigned to both activities, hence the overallocation error showing in the info column (red human icon).
Why do I require such a structure you may ask? In reality, one task would continually be temporarily interrupted to do the other one, and vice versa. But in MSP, it would be counter-productive to do so. Hence, my simplified approach - parallel activities.
So how should I fix this issue?
- Ignore it?
- Allocate 50% of the resource to each (and fix up finish dates which are automatically extended by MSP?)
- Or is there a better solution?