我正在使用石英调度程序来安排我的工作。我用过 CronTrigger。但问题是触发器被再次触发一次。这是我设置 cron 调度程序的代码..
SchedulerFactory schFactory = new StdSchedulerFactory();
Scheduler sched = null;
CronTrigger cronTrigger = null;
try {
sched = schFactory.getScheduler();
JobDetail jobDetail = new JobDetail("job1", "group1",SchedulerPBGC.class);
String cronTimerStr = "* 16 15 * * ? *";
LOG.warn("CRON TRIGGER FORMAT FOR PROCESSING PB GC DATA:"+cronTimerStr);
cronTrigger = new CronTrigger("SchedTrigger", "Group1", cronTimerStr);
sched.scheduleJob(jobDetail, cronTrigger);
sched.start();
LOG.warn("SCHEDULER REGISTERED FOR PROCESSING PB GC DATA : TIME :"+cronTimerStr);
} catch (SchedulerException se) {
LOG.error("SchedulerException Message::"+se.getLocalizedMessage());
}
在这里,我的调度程序执行了 10 次作业......在这里你可以看到日志......
2012-06-20 15:16:50,001 DefaultQuartzScheduler_Worker-1 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION STARTED-----------------------
2012-06-20 15:16:50,001 DefaultQuartzScheduler_Worker-1 WARN test.SchedulerPBGC - The value of NO_OF_BEFORE_DAY_TO_RUN must be less then zero ..to start the scheduler
2012-06-20 15:16:50,001 DefaultQuartzScheduler_Worker-1 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION COMPLETED-----------------------
2012-06-20 15:16:51,001 DefaultQuartzScheduler_Worker-2 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION STARTED-----------------------
2012-06-20 15:16:51,001 DefaultQuartzScheduler_Worker-2 WARN test.SchedulerPBGC - The value of NO_OF_BEFORE_DAY_TO_RUN must be less then zero ..to start the scheduler
2012-06-20 15:16:51,001 DefaultQuartzScheduler_Worker-2 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION COMPLETED-----------------------
2012-06-20 15:16:52,001 DefaultQuartzScheduler_Worker-3 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION STARTED-----------------------
2012-06-20 15:16:52,001 DefaultQuartzScheduler_Worker-3 WARN test.SchedulerPBGC - The value of NO_OF_BEFORE_DAY_TO_RUN must be less then zero ..to start the scheduler
2012-06-20 15:16:52,001 DefaultQuartzScheduler_Worker-3 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION COMPLETED-----------------------
2012-06-20 15:16:53,001 DefaultQuartzScheduler_Worker-4 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION STARTED-----------------------
2012-06-20 15:16:53,001 DefaultQuartzScheduler_Worker-4 WARN test.SchedulerPBGC - The value of NO_OF_BEFORE_DAY_TO_RUN must be less then zero ..to start the scheduler
2012-06-20 15:16:53,001 DefaultQuartzScheduler_Worker-4 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION COMPLETED-----------------------
2012-06-20 15:16:54,001 DefaultQuartzScheduler_Worker-5 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION STARTED-----------------------
2012-06-20 15:16:54,001 DefaultQuartzScheduler_Worker-5 WARN test.SchedulerPBGC - The value of NO_OF_BEFORE_DAY_TO_RUN must be less then zero ..to start the scheduler
2012-06-20 15:16:54,001 DefaultQuartzScheduler_Worker-5 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION COMPLETED-----------------------
2012-06-20 15:16:55,001 DefaultQuartzScheduler_Worker-6 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION STARTED-----------------------
2012-06-20 15:16:55,001 DefaultQuartzScheduler_Worker-6 WARN test.SchedulerPBGC - The value of NO_OF_BEFORE_DAY_TO_RUN must be less then zero ..to start the scheduler
2012-06-20 15:16:55,001 DefaultQuartzScheduler_Worker-6 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION COMPLETED-----------------------
2012-06-20 15:16:56,001 DefaultQuartzScheduler_Worker-7 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION STARTED-----------------------
2012-06-20 15:16:56,001 DefaultQuartzScheduler_Worker-7 WARN test.SchedulerPBGC - The value of NO_OF_BEFORE_DAY_TO_RUN must be less then zero ..to start the scheduler
2012-06-20 15:16:56,001 DefaultQuartzScheduler_Worker-7 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION COMPLETED-----------------------
2012-06-20 15:16:57,001 DefaultQuartzScheduler_Worker-8 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION STARTED-----------------------
2012-06-20 15:16:57,001 DefaultQuartzScheduler_Worker-8 WARN test.SchedulerPBGC - The value of NO_OF_BEFORE_DAY_TO_RUN must be less then zero ..to start the scheduler
2012-06-20 15:16:57,001 DefaultQuartzScheduler_Worker-8 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION COMPLETED-----------------------
2012-06-20 15:16:58,001 DefaultQuartzScheduler_Worker-9 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION STARTED-----------------------
2012-06-20 15:16:58,001 DefaultQuartzScheduler_Worker-9 WARN test.SchedulerPBGC - The value of NO_OF_BEFORE_DAY_TO_RUN must be less then zero ..to start the scheduler
2012-06-20 15:16:58,001 DefaultQuartzScheduler_Worker-9 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION COMPLETED-----------------------
2012-06-20 15:16:59,001 DefaultQuartzScheduler_Worker-10 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION STARTED-----------------------
2012-06-20 15:16:59,001 DefaultQuartzScheduler_Worker-10 WARN test.SchedulerPBGC - The value of NO_OF_BEFORE_DAY_TO_RUN must be less then zero ..to start the scheduler
2012-06-20 15:16:59,001 DefaultQuartzScheduler_Worker-10 WARN test.SchedulerPBGC - ----------PB GC SCHEDULER EXECUTION COMPLETED--------------------
如何将 CronTimer 迭代器设置为 1 ?或者我怎样才能停止调度程序多次执行作业。
有什么建议吗?谢谢,Gunjan Shah。