1

I created a snapshot view, all view access properties show the date i created it, date last modified, last accessd etc.. are all the date it should be April 10 BUT the Configurations tab shows a foundation baseline of the next release up May 10

Now I do it difrent; I create a child stream created with the older baseline and then make a snapshot but I would like to know why this snapshot I made 4/10 has a foundation baseline of 5/10 Weird how it shows a foundation baseline that is newer than the date it was created, Maybe CC just knows this is the foudantion of this next release i guess

I did a compare and the files are still the same as the date I created the snapsot is appears but if not I am in trouble...

I am new to CC and devolpement Thanks in advance

4

1 回答 1

0

没有什么可以阻止任何人从antoehr视图中更改您查看的 Stream 所基于的基础。

然后,当您更新快照视图时,ClearCase 将检测到 Stream 的配置更改,并建议将您的视图的配置规范与 Stream 同步。
因此,您的视图配置发生了变化。

您在这种情况下所做的事情是正确的:根据正确的基线创建一个子 Stream,然后从那里开始工作。

请参阅“变基操作”:

变基

Pat 的开发流中的一个组件配置了 baseline BL1
变基操作将流的配置BL2从集成流更改为基线。
变基操作将文件和目录从集成流或特定于功能的开发流合并到开发流。

于 2012-05-16T17:51:05.223 回答